Why the delay in the York Street Interchange project is detrimental to the Northern Ireland economy

Thursday 09 August 2018

Statement by Seamus Leheny, FTA’s Northern Ireland Manager

The news the £130 million improvement scheme to Belfast’s York Street is facing delays due to errors in its procurement strategy has been met with frustration by the Freight Transport Association, an organisation representing more than 17,000 businesses across the UK logistics sector.

When the scheme was first announced around nine years ago, local business involved in Transport of goods greeted the project with a sign of relief. The junctions around Belfast’s M1, M2 and M3 experience very high levels of traffic which can cause long delays to all road users whether they are commercial vehicle operators, public transport or private car drivers and it wasn’t a sustainable system. By improving journey time reliability, traffic flow and lowering emissions, the project was set to help commercial vehicle operators move goods across Northern Ireland more swiftly and efficiently boosting the Northern Ireland economy in the process.

Yet again the scheme faced another delay this week, with the High Court ruling there were mistakes in the way the Department for Infrastructure appointed a contractor. Every day the project is delayed, Belfast’s roads become more congested and difficult to navigate. As commercial vehicle operators continue to face unnecessarily long journey times, the industry’s ability to move goods across the North efficiently becomes compromised. As a region, in terms of connectivity and infrastructure we also continue to fall behind the Republic of Ireland and Great Britain which is a significant influencing factor for inward investment.

Despite facing several setbacks since its inception, most prominently in recent years a lack of funding, the project is now fully viable with funding secured via the DUP and Conservative Party Confidence and Supply agreement of June 2017. Our concern now is that in the interim period of another delay, the project could suffer even more severe setbacks if that political agreement were to be compromised.

The High Court ruling is the sole obstacle it now faces. If the scheme collapsed due to this procurement error, it would be a serious setback to the prosperity of the logistics sector, and in turn, the wider Northern Ireland economy.

Whatever the outcome of the hearing, FTA hopes the plans for the scheme will stay in place, and its members along with the wider public will have the chance to benefit from a much-improved York Street Interchange.   

Efficient logistics is vital to keep Britain trading, directly having an impact on more than seven million people employed in the making, selling and moving of goods.  With Brexit, new technology and other disruptive forces driving change in the way goods move across borders and through the supply chain, logistics has never been more important to UK plc.  A champion and challenger, FTA speaks to Government with one voice on behalf of the whole sector, with members from the road, rail, sea and air industries, as well as the buyers of freight services such as retailers and manufacturers.